Friday, March 2, 2012

Field Report as of March 2, 2012


As construction crews were completing earth moving activity, ground water was found on the site.  The excess water caused the soil to fail compaction requirement testing.  Lime was brought in and mixed with fill soil to aid in compaction.  Testing has been completed and the site now exceeds compaction requirements for footings and foundations.

Layouts for footings and foundations were prepared and the first footing was poured on Wednesday, February 29.  